Due to the new plumbing work which found its way into the sacristy, the walls were going to need some patching and painting. As a bonus, the entire sacristy is being painted. It definitely needed to be freshened up.
A carpenter from the organ company is working in place in the loft to get precise measurements for the cabinetry.
As part of the plan to control where rainwater goes, stained and sloped concrete is now in place in the courtyard between the sanctuary and the Harris Wing.
While up on their ginormous lift, the painters are cleaning our clerestory windows! Are you even ready for all that sunshine?
We chose a slightly lighter shade for the panels behind Jesus and the cross. Look up to the top to see the difference between the lighter shade and the overall shade. Also, the bronze Jesus statue and cross have had a much-needed thorough cleaning.